PROJECT DESCRIPTION:
To interconnect the proposed COB Energy Facility (Peoples Energy Resources Corp.). The 1200 MW combustion turbine project would be constructed in two 600 MW phases at a site near Bonanza, Oregon. Phase I is scheduled to energize in June 2004. The project is subject to the Oregon Energy Facility Site Certification (EFSC) process managed by the Oregon Office of Energy (OOE).
CONTACT:
For further information on this project, please contact ECAdmin@bpa.gov or 503-230-4628.
DOCUMENTS:
RECORD of DECISION:
Rceord of Decision (08/20/2004)
FINAL EIS:
Final EIS (Complete) (June 2004)
Public Letter (01/13/2004)
DRAFT EIS:
Draft EIS (Table of Contents) (November 2003)
NOTICE of INTENT:
Notice of Intent - Letter w/attachment (12/21/2001)