PROJECT DESCRIPTION:
Bonneville Power Administration (BPA) proposes to rebuild an existing 115-kV transmission line, between Raymond and Cosmopolis, roughly parallel to Hwy 101. Most of the 18.3-mile long transmission line would remain within the existing right-of-way, but some structures would be moved due to environmental or engineering constraints.
CONTACT:
For further information on this project, please contact Kimberly St.Hilaire, BPA Environmental Lead.
DOCUMENTS:
FINAL EA / FONSI:
Public Letter (09/05/2003)
Final EA and FONSI (08/22/2003)
Final EA and FONSI formatted for printing
PRELIMINARY EA
Preliminary EA (Abridged) (01/28/2003)
Public Letter (01/21/2003)
Comment Form (03/28/2002)