PROJECT DESCRIPTION:
Pacific Power will construct, operate, and maintain a new 230-kilovolt (kV) transmission line from Pacific Power's Pomona Heights substation located east of Selah, Washington, in Yakima County, to the Bonneville Power Administration (BPA) Vantage Substation located east of the Wanapum Dam in Grant County, Washington. The existing Pacific Power Pomona Heights substation and BPA's Vantage substation will interconnect the new 230-kV transmission line to the regional electric grid.
The Bureau of Land Management (BLM) was the lead federal agency responsible for the preparation of an environmental impact statement (EIS) that addressed the potential effects of the Vantage to Pomona Heights 230-kV Transmission Line Project. BPA was a cooperating agency for the EIS. Additional project information can be obtained through the BLM Website.
CURRENT STATUS:
In October of 2017, BPA decided to interconnect the Vantage to Pomona Heights transmission line into the Federal Columbia River Transmission System (FCRTS) via the Vantage Substation. BPA’s construction activities are anticipated to start in early 2019.
PROJECT SCHEDULE:
Scoping comment period |
January 5 to March 8, 2010 |
Scoping public meetings |
February 3 and 4, 2010 |
Draft EIS available for public comments |
January 4, 2013 |
Supplemental Draft EIS comment period |
January 2, 2015 to February 17, 2015 |
Supplemental Draft EIS public meetings |
January 28 and 29, 2015 |
Final EIS |
October 21, 2016 |
Record of Decision |
October 3, 2017 |
CONTACT: For environmental information contact: Katey Grange Environmental Protection Specialist Bonneville Power Administration - ECT-4 P.O. Box 3621 Portland, OR 97208-3621
For project information contact: Rasha Kroonen Project Manager Bonneville Power Administration - TEPP-TPP-1 P.O. Box 61409 Vancouver, WA 98666-1409 |
Toll Free: 800-622-4519 Direct Line: 503-230-4047 Email: kcgrange@bpa.gov
Toll Free: 800-622-4519 Direct Line: 360-619-6918 Email: rmkroonen@bpa.gov |
DOCUMENTS:
ROD
Record of Decision (10/3/2017)
Federal Register Notice of Availability (10/16/2017)
FINAL EIS:
BLM Public Letter (10/21/2016)
Final EIS (10/21/2016)
Appendix A - Project Maps
Appendices B1-B3
Appendices B4-E
Appendices F-I
SUPPLEMENTAL DRAFT EIS:
BLM Public Letter
Supplemental Draft EIS (01/02/2015)
Appendix A1 Maps
Appendix A2 Maps
Appendices B-E
DRAFT EIS:
BLM Public Letter
Draft EIS (01/04/2013)
Appendix A
Appendix B
Appendix C
Appendix D