PROJECT DESCRIPTION:
The Bonneville Power Administration (BPA) has decided to fund the construction and operation of a spring Chinook hatchery on the South Fork Walla Walla River near Milton-Freewater in Umatilla County, Oregon. The hatchery will be located at the site of an existing adult holding and spawning facility managed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR), who will also operate the proposed hatchery. The hatchery will incubate and rear spring Chinook salmon, which were extirpated from the Walla Walla River basin in the early to mid-1900s. The project would augment fish populations available for harvest and aid in establishing a naturally spawning spring Chinook population in the Walla Walla basin.
ENVIRONMENTAL REVIEW:
To understand the potential environmental impacts of this proposal, BPA prepared an environmental impact statement (EIS) following the procedures of the National Environmental Policy Act (NEPA). The EIS analyzes two action alternatives and a no action alternative. The EIS describes anticipated impacts to natural and human resources, as well as mitigation measures to help avoid or minimize impacts
CURRENT STATUS:
BPA has prepared a Record of Decision, which explains the factors that were considered in reaching the decision to fund the Walla Walla Basin Spring Chinook Hatchery Program, and a Mitigation Action Plan that lists the measures that will be used to avoid or reduce environmental impacts.
PROJECT SCHEDULE:
Scoping comment period Scoping meetings Additional scoping comment period Draft EIS comment period Public meetings Final EIS ROD If decision to build, construction start |
March 28, 2013 - May 15, 2013 April 16, 2013 in Milton-Freewater, OR and April 17 in Dayton, WA June 2, 2014 - July 1, 2014 October 7, 2014 - November 24, 2014 October 29, 2014 in Dayton, WA and October 30, 2014 in Milton-Freewater, OR May 25, 2018 August 31, 2018 Fall 2018 |
CONTACT:
For environmental information, contact: Carolyn Sharp Environmental Protection Specialist Bonneville Power Administration - ECF-4 P.O. Box 3621 Portland, OR 97208-3621 |
Toll-free: 800-622-4519 Direct line: 503-230-5206 Email: casharp@bpa.gov |
For project information, contact: Gerald McClintock Project Manager Bonneville Power Administration - EWB-4 P.O. Box 3621 Portland, OR 97208 - 3621 |
Toll-free: 800-622-4519 Direct line: 503-230-5375 Email: gmcclintock@bpa.gov |